PROJECT
Moreton Bay Rail
Moreton Bay Rail involved the delivery of a 12.6km dual track passenger line from the existing Petrie Station through to Redcliffe (Kippa-Ring). The project was a collaborative Design & Construct contract between Thiess and Department of Transport and Main Roads.

PROJECT HIGHLIGHTS
Location
Brisbane, Queensland
Client
Queensland Rail (QR)
Department of Transport and Main Roads (DTMR)
City of Moreton Bay (CMB)
Project Value
$1.3 billion
Contract Period
February 2012 to March 1026 (DTMR/QR)
January 2013 to June 2017 (CMB)
PROJECT BACKGROUND
The Moreton Bay Rail project delivered a new dual track passenger line from Petrie to Kippa-Ring, a grade separated rail junction at Petrie, and quadruplication of the North Coast line between Lawnton and Petrie. This project is reccognised as a region-building initiative and was funded by all three levels of government. DTMR delivered the project for Queensland Rail to operate and maintain. City of Moreton Bay (CMB) was a key stakeholder and participant of the project, taking ownership of key assets following the project.
The project also included two HV feeder stations, new signalling interlocking technology and stabling facilities for 10 electric trains near Kippa-Ring. Six new stations were constructed at Kallangur, Murrumba Downs, Mango Hill, Mango Hill East, Rothwell, and Kippa-Ring, as well as a new island platform at Petrie.
Rail corridor works included:
- Civil and structures, earthworks, rail bridges and structures, drainage works, retaining walls, noise barriers, and other rail corridor works
- Stations and precincts, platforms, buildings, carparks, landscaping, security, lighting, internal roads and connection to the local road network
- Rail systems, including track, signalling, overhead electriciation, communications, and operational systems.
City of Moreton Bay works included:
- Civil and structures - detailed design and construction of earthworks, drainage, flexible pavement, road over rail and shared path bridge structures, retaining walls, noise barriers and construction of a shared user path facility along the length of the rail alignment
- Landscaping, lighting, signalised intersections, and connection to the local road network.
CPM provided services to both DTMR/QR and CMB.
CPM SCOPE OF WORK
The scope of works for DTMR/QR included:
- Produced a comprehensive Scope of Works and Technical Criteria (SWTC) to provide the technical brief and specification and specify the minimum mandatory requirements for design and construction of the project as an input to the dual ECI process and the D&C contract
- Assisted DTMR to develop funding and interface agreements wtih Federal and Local Government and Queensland Rail. Faciliated planning approvals required for the project
- Design integration and management of design reviews for the rail corridor and rail systems design for DTMR and Queensland Rail. Management of changes, reviews, and input from technical specialists during the D&C contract
- Established and implemented an Assurance and Handover Plan for Queensland Rail to perform sufficient due diligence of the construction and commissioning to allow acceptance of the asset
- Established and implemented a Rail Safety Change Management Plan to manage the transfer of Rail Infrastructure Manager from the constructor to Queensland Rail. This involved close interaction and ongoing liaison with the Rail Safety Regulator
The scope of works for CMB included:
- Developed Handover Specifications for project
- Developed Handover Agreement between State and CMB
- Managed and led handover of Kinsellas Road early works from DTMR to CMB
- Collated and confirmed project specifications including Council requirements
- Construction Surveillance Management (Independent Verification) of all project assets to be handed over to CMB as asset owners
- Coordinated the interface between construction and the asset owners (CMB)
- Managed and led handover of assets from DTMR to CMB including document verification to ensure handover requirements were achieved.
KEY ACHIEVEMENTS
Drove the project to maintain critical path for delivery using strong governance knowledge and early stakeholder engagement.