PROJECT

The Mill Redevelopment

The Mill at Moreton Bay Priority Development Area (PDA) is approximately 460 hectares and is located within the suburbs of Petrie, Kallangur and Lawnton. Moreton Bay Regional Council is creating a thriving major destination that will generate thousands of local higher education and employment opportunities in the region. 

With a full-scale University of the Sunshine Coast (USC) Campus at its core, this new destination offers world-class study opportunities for residents in the Moreton Bay Region. 

Petrie Mill Development

Location

Petrie, Queensland

Client

City of Moreton Bay

Project Value

$95 Million

Contract Period

September 2016 - December 2017

PROJECT BACKGROUND

CPM was first engaged in 2016 to work within the MBRC Major Projects team to plan and deliver the precinct and its enabling infrastructure to support the development of a new university opening in 2020.

CPM provided Project Management Services to coordinate and manage the various design consultants to establish the Preliminary Design and Site Establishment for Stage 1.

Following this CPM was further engaged to provide Construction Management Services as part of MBRC delivery team. This scope involved:

  • Site Remediation
  • PUP Relocations
  • Bulk Earthworks
  • Civil Infrastructure (State Network)
  • Civil Infrastructure (Subdivision/Development Works)
  • Parks and Recreation

CPM provided the MBRC team with resources which included Project Managers, Contract Administrators, Senior Construction Engineers, Construction Engineers, Project Engineers, Civil Inspectors and Landscape Inspectors.

Key milestone dates for the project included:

  • 2015: Moreton Bay Regional Council acquired former Amcor Paper Mill site
  • 2016: “The Mill” declared the region’s Priority Development Area by the State Government
  • 2017: Design and early works
  • 2018-2020: Stage 1 Construction
  • 2020: University Sunshine Coast Moreton Bay Campus Opened
  • 2023: Remediation of contamination complete
CPM SCOPE OF WORK

CPM was engaged to provide Project Management Services to co-ordinate and manage the design consultant through the preliminary design and site establishment phase. The contract was extended to include contract administration and inspection services during the construction phase.

The work included coordinating and supporting MBRC internal staff through:

  • Design Management through Preliminary Design Phase
  • Development of Scope of Work and Technical Criteria for detailed design phase
  • Overall Project Risk Assessment
  • Transaction management through the early works and construction phase
  • Prepare council briefing & recommendations papers
  • Co-ordination of external consultants and internal MBRC Departments
  • Review project estimates, risk modelling, reports, and other relevant project information
  • Develop and prepare, programs, tender documents and budgets.
  • Lead, facilitate and manage project meetings, workshops and stakeholder working groups
  • Contract Administration
  • Verification and Inspection
  • Simultaneous Operations Co-ordination.
KEY ACHIEVEMENTS

The project was delivered on time while closely managing and monitoring material supply rates with significant time and cost savings, while reducing the risk of contamination. 

RELATED PROJECTS
The Wave Sunshine Coast Rail Line Concept Rendering

The Wave (Sunshine Coast Rail Line)

The Wave is a major Queensland Government public transport initiative delivering a new passenger rail line from Beerwah to Birtinya, with a metro-style connection to the Sunshine Coast Airport via Maroochydore. Sunshine Coast Council engaged CPM to provide strategic advisory and technical support to negotiate an Interface Deed with the Department of Transport and Main Roads (TMR), ensuring Council’s long-term interests, obligations and community outcomes are protected across all stages of this transformational project.

Mahon Bridge, Lockyer Valley

Mahon Bridge

This project was the replacement of the existing concrete bridge that was constructed in 2009 and damaged in the January 2013 flood event. Following the floods a number of deficiencies were identified with the bridge which necessitated a load restriction to be imposed and a reduction in capacity from two to one lane. A funding submission was required to secure funding for the new bridge.

Flood affected road in Toowoomba region

DTMR Darling Downs Disaster Recovery

The DTMR Darling Downs district was affected by multiple flood disaster events across 2021 and 2022. The events triggered the requirement for various projects across the road network under DRFA, NDRRA, Emergent works and Betterment funding categories.